MATERIALS AND ELEMENTS · concrete

Concrete Mix Calculator

What to buy, how to batch it, and how long before you can stand on it.
ratios by volume · 1.54× dry factor
0.475 m³ · C20

What are you pouring?

Grade

Water

0.50

Buying

Ballast is sand and aggregate pre-blended. One material to order and store, but you lose the ability to adjust the ratio on site.

Cement bag size

Wastage

10%

Spillage, an uneven sub-base and material left in the mixer. Running out part-way through a pour is far worse than over-ordering — a cold joint is a permanent weak line.

Order this much
—

Mixer

40 L
Concrete produced per batch, not drum size — a 90 litre drum makes roughly 40 litres at a time.

You’ll need

—
Cement bags
—
Sand
—
Aggregate
—

Water is the strength dial

—

When can you use it?

—

One mixer load

—
How it works

Ratios by volume, one correction factor, and two curves

Ratios by volume

Grades are nominal mixes of cement : sand : aggregate, 1:2:4 for C20 through 1:1.5:3 for C30, batched by volume with a bucket. This page turns each share into a weight with its own bulk density.

The 1.54× factor

Paste and water fill the gaps between loose particles, so you need about 1.54× the finished volume in dry material. Skipping it is the commonest reason people under-order.

Water is the dial

Set by the water-cement ratio you choose, and a stronger lever on final strength than the mix ratio. Each grade caps the water you can add and still reach it.

Strength over time

The Eurocode 2 curve for class N cement, stretched by temperature through a maturity calculation: cold slows the reaction, it does not stop it.

Worked example. A 0.475 m³ shed base at C20 (1:2:4) with a 10% allowance needs about 166 kg of cement (6.6 bags of 25 kg), 368 kg of sand and 690 kg of aggregate, plus 83 litres of water. That is 14 loads through a 40-litre mixer. At 12°C it takes about 6 days to reach the 70% you want before driving on it. Bars share one scale of 690.
Field notes

What actually decides whether the slab is any good

Water is the strength dial, and it only turns one way

Water-cement 0.50100%
0.60 · two extra litres a bagabout 75%
0.70nearly half

Relative final strength; strength falls roughly exponentially with the ratio. Nothing else you control on site moves the number that far. Wetter is easier to place and worse forever, and the damage is invisible until something cracks.

Cement is the glue, not the bulk

Cement is only 1 part in 7 of a C20 mix by volume. Sand and aggregate carry the load; cement binds them. More cement is not automatically stronger: the ratio matters more than the quantity, and an over-rich mix shrinks and cracks.

Batch by bucket, never by shovel

A shovel of damp sand and a shovel of dry cement are nothing like the same volume, and the error compounds over every load. Nominal ratios are volume ratios, so a bucket is the correct instrument. All-in ballast is one material instead of two, with the parts added together: 1:6 for C20, 1:5 for C25, 1:4.5 for C30.

×2as long

Cold does not weaken concrete, it slows it down

At 5°C the hydration clock runs at half its 20°C speed, so the same slab takes twice as long to reach the same strength; at 10°C about two thirds. Freezing before it sets is different and permanent: that damage does not come back. The familiar “70% at seven days” is a British answer; at 20°C you get there in under five days.

A cold joint is forever

Concrete poured onto a batch that has already stiffened does not bond to it. In a slab mixed load by load over several hours, those planes are where it will eventually crack, which is why volume, not effort, is the real argument for ready-mix. Around a cubic metre (roughly 25 loads through a small mixer) is where to stop mixing it yourself.

Curing is not drying

Concrete gains strength by reacting with water, not by losing it. A slab left to dry out in sun or wind stops gaining strength early. Cover it, keep it damp for the first week, and the 28-day figure means something.

Questions

What people ask

Why does the mix need more dry material than the finished volume?

Loose sand and aggregate have air gaps between the particles, and when cement paste and water fill those gaps during mixing the total volume shrinks. The 1.54× factor is the standard correction for that settling. It is an average: very coarse or very fine aggregate will shift it, which is part of why a wastage allowance is not optional.

Does adding water really matter that much?

More than anything else you control on site. Strength falls roughly exponentially with the water-cement ratio, so going from 0.50 to 0.60 — about two extra litres per 25 kg bag, which looks like nothing in a mixer — costs around a quarter of the final strength. At 0.70 you have lost nearly half. A wetter mix is easier to place and worse forever afterwards, and the damage is invisible until something cracks.

Which grade should I actually use?

C20 handles the vast majority of domestic jobs — shed bases, patios, footings — and is the easiest to batch by hand. Step up to C25 anywhere vehicles will drive or park, and C30 only for structural elements like beams or columns, where hand-mixing consistency becomes hard to guarantee. Each grade also caps how much water you can use and still reach it, which this page checks against the ratio you have set.

Can I use all-in ballast instead of separate sand and aggregate?

Yes, and it is one material to order rather than two. Ballast is pre-blended, so the equivalent ratio is simply the sand and aggregate parts added together: 1:6 for C20, 1:5 for C25 and 1:4.5 for C30. Merchants often quote 1:5 as a general-purpose mix, which sits between C20 and C25 here. What you give up is the ability to adjust the sand fraction on site when the mix looks wrong.

Why does the curing time change with temperature?

Because cement hydration is a chemical reaction and cold slows it down. The page uses a maturity calculation with a −10°C datum, which is the standard approach: at 10°C the clock runs at about two thirds the speed it does at 20°C, and at 5°C roughly half. This is why the familiar “70% at seven days” figure is a British answer rather than a universal one — at 20°C you get there in under five days.

At what point should I stop mixing it myself?

Around a cubic metre. That is roughly 25 loads through a small mixer, and every load has to be batched, mixed, barrowed and placed before the previous one has stiffened. Beyond that the real risk is not effort but cold joints, because a slab poured over several hours in separate batches has weak planes through it. The page flags the crossover as the volume climbs.

A material-quantity estimate, not a structural design. Real mixes vary with aggregate size, moisture content and supplier specifics, and the strength figures here are indicative shapes rather than a prediction for your batch. For anything load-bearing or structural, use a designed ready-mix, not a hand-batched estimate.
Version history · site-wide passes only

This page has changed in 161 archived releases, but each of those was a site-wide pass, so none is attributable to this tool on its own and none is listed here. That is not a claim that the tool never changed — a release that reworked many pages at once may well have altered this one too. The changelog has them.

Rules of thumb are approximations, offered to get you to the right order of magnitude fast. Check anything load-bearing against its source or the exact tool. Privacy · Terms

© 2026 Rules of Thumb · Runs entirely in your browser